For people in design

Make Your Selections Before You Bid

An allowance is a decision you haven't made yet, priced by someone else. Every allowance in a bid is the builder's guess at what you'll pick, and every one of them can move after you sign.

The most reliable way to shrink that risk is boring: make more of your selections before the bids go out. Each one you make turns a placeholder into a line item with a real product and a real price. The bid gets shorter, more accurate, and easier to compare.

Which selections matter most

Not every selection carries the same weight. The ones worth deciding early are the ones that cost the most, take the longest to arrive, or change how the house gets built.

Windows and exterior doors. Usually one of the biggest single packages in the house, and often one of the longest lead times. The brand, the frame material, and the glass all change the price.

Cabinets. Construction type, material, door style, and interior fittings add up fast. A cabinet allowance can cover very different kitchens.

Tile and stone. Price per square foot, how high it goes, the pattern, and the size of the tile all change both material and labor.

Plumbing fixtures. Faucets, shower valves, tubs, toilets. Counting the valves and outlets in each shower is one of the fastest ways to firm up a number.

Lighting. Decorative fixtures vary enormously in price, and heavy ones can need blocking in the ceiling before drywall.

Appliances. They set cabinet dimensions, electrical and gas requirements, and sometimes venting. A late appliance change can mean rework.

Flooring. Wood species, width, finish, and whether it's site-finished or prefinished.

Which can wait

Some selections don't move the price much or don't affect how the house is built, so they can come later without much risk.

  • Cabinet and door hardware, as long as the allowance is realistic
  • Paint colors, as long as the paint system is defined
  • Some decorative lighting, as long as the locations and any heavy fixtures are known
  • Accessories like towel bars and mirrors

The test is simple. If changing your mind later would mean tearing something out or moving a wire, pipe, or wall, decide it early.

How to work through it

Take the drawings with you. A showroom visit goes much better when you can point to the room on the plan and the salesperson can see the dimensions.

Keep one selections list, room by room: the item, the product or model number if you have it, the price, and a photo. A spreadsheet is fine. Where you haven't picked an exact product, write down the type and level clearly, like "thermostatic valve, three outlets, matte black" or "5-1/2 inch site-finished white oak."

Then send that list to every builder with the drawings. It does two things: it gives everyone the same target, and it turns allowances into line items. See How to get builder bids you can actually compare.

What changes in the bid

Here's the same lighting line, before and after the selections are made. Illustrative numbers.

LightingBeforeAfter
How it appears in the bidAllowanceLine items
Amount$12,000$19,400
Will it change after signing?Almost certainlyOnly if you change it

The "after" number is higher. That's the point. The money was always going to be spent. Making the selection early just moves the surprise from after you sign to before, when you can still do something about it. See Allowance math.

The schedule side

Selections aren't only about price. Every product has to be chosen, then ordered, then delivered before it can be installed. A late decision on windows or cabinets can hold up a trade, and that trade can hold up the next one. Building a selections schedule with dates is one of the most useful things you can do. See How long a custom home takes.

Questions worth asking

  • Which of my selections have the longest lead times?
  • By what date do you need each selection to keep the schedule?
  • Which allowances could you turn into line items if I picked the product now?
  • Does each allowance cover material only, or material and installation?
  • What markup applies if a selection comes in over its allowance?
Fewer allowances, fewer surprises.