Sample

What a Talus Review Looks Like

You send the bids, the drawings they were priced from, and anything that describes the finish level you have in mind: a finish brief, photos, a specification. I read them side by side and send back a short written summary, always in the same format, so you know where to look.

Below is a complete sample. The project is fictional and every number is illustrative. It's a bid leveling summary for two bids; a single bid review uses the same headings without the side-by-side table.

Illustrative sample · fictional project

Talus bid review: Rivera Residence

Bid leveling · Delivered February 9, 2027 (illustrative)

1. Project and documents reviewed

  • Clients: Alex and Sam Rivera
  • Project: Rivera Residence, a new single-family home
  • Bids: Sample Builder A, $1,180,000, 14 pages. Sample Builder B, $1,215,000, 22 pages.
  • Drawings: permit set, 18 sheets, the same dated set for both bids
  • Also reviewed: the Riveras' one-page finish brief with photos
  • Not provided: specifications (none issued for this project)

Side by side

Sample Builder ASample Builder B
Bid total$1,180,000$1,215,000
Allowances, total$120,000$175,000
Allowances raised to a common level+$55,000$0
Excluded scope, priced (driveway)+$30,000included
Leveled total$1,265,000$1,215,000

The common allowance level is Builder B's, because B's allowances line up with the finish brief. The driveway figure is a separate quote the Riveras already had.

2. What's missing

Snowmelt at the front walk and entry landing. Shown on the civil sheet (C1.1) with a boiler loop note. Neither bid prices it, so it doesn't change the comparison, but it isn't in either number. Ask both builders to price it as an alternate.

Exterior stair from the lower deck to grade (Builder A). Shown on A3.2. Builder A's deck line reads "deck per plans" and lists the upper deck framing, decking, and railing, with no mention of the lower deck stair. Builder B lists both decks and the stair. Worth a written yes or no from A before you compare further.

3. Allowances that look light

AllowanceCarried (A)What you describedWhy it looks light
Lighting fixtures$12,000Pendants over the island, a dining fixture, sconces in every bathCovers recessed cans and a few basic decorative pieces. Builder B carries $25,000.
Plumbing fixtures$16,000Thermostatic shower with a handheld and a rain head in the primary bathThe primary shower valve and trim you showed could use a large share of this alone.
Tile, material$18,000Tile to the ceiling in the primary shower, large-format floors in all bathsWorks out to roughly a basic porcelain at the square footage on the drawings.

Builder A's bid says overages carry a 15% markup. Builder B's says 10%. That difference matters more as the overages grow.

4. What's vague

  • "Trim package per plans" (Builder A, page 6): the drawings don't show trim profiles or base height. Ask what casing and base were priced, and whether it's paint-grade or stain-grade.
  • "Site work: excavation and backfill, standard" (Builder A, page 3): no assumption about rock or groundwater. Ask what happens if they hit rock, and at what rate.
  • "Appliances by others" (Builder B, page 9): clear that appliances aren't in the number, but not whether installation and hookup are. Ask who installs them and whether that's priced.

5. Five questions for your builder

  1. Builder A: would you reprice with our allowance amounts (attached), so both bids carry the same placeholders?
  2. Builder A: is the lower deck stair on A3.2 included? If not, what would it add?
  3. Both: what would the snowmelt at the front walk and landing add, as an alternate?
  4. Builder A: what trim profiles, base height, and grade did you price under "trim package per plans"?
  5. Both: what's your rock assumption for excavation, and how is rock removal priced if you hit it?

Construction review only, not legal advice.

Every review uses these same headings in the same order. If a heading has nothing to report, it says so in one line rather than disappearing. The questions are written so you can paste them into an email to your builder.

Get yours.

A single bid review is $750, back within five business days. Leveling for two or three bids is $1,250, back within seven business days.